PRODUCTION · ASTURIAS

Asturias: A Hydrogen Hub Built Around the Industry That Will Use It

Much of the hydrogen conversation stops at the electrolyser. Asturias goes further — pairing a planned 150 MW production hub with the industry that will consume its hydrogen, on the site of the Aboño power plant: a former coal plant whose Unit 2 now runs on natural gas, through burners built to take hydrogen too. It is a full-stack answer, built on the bones of the region's fossil-fuel past.

Green hydrogenIndustrial decarbonisationElectrolysisPower-plant retrofitJust transitionProduction
Aboño thermal power plant · Gijón · Asturias · Photo: Borvan53, CC BY-SA 4.0, via Wikimedia Commons
150 MW
planned first-phase electrolyser capacity
~20,000 t
green hydrogen a year, by design
~130 kt
CO₂ a year the hub is designed to avoid
PROJECT PARTNERS
EDP — Project lead · hub developer & Aboño owner

Consortium lead for Asturias. EDP is developing the Asturias H2 Valley — a green-hydrogen hub on the Aboño site. With Corporación Masaveu, through their 50/50 joint venture Aboño Generaciones Eléctricas, it has also converted the plant's Unit 2 from coal to natural gas, using burners designed to burn hydrogen as well.

ALSA — Mobility partner

Consortium partner and regional passenger-transport operator — a hydrogen-bus mobility pathway (its H2-bus test starts in Madrid and transfers to Asturias once fuelling is available).

HIDRITEC — Water treatment · electrolysis

Consortium partner developing and manufacturing a demineralised-water treatment container adapted for a large (≈100 MW-scale) electrolysis plant like the one foreseen at the EDP site.

FAEN — Asturian Energy Foundation (associated)

Associated partner — the Fundación Asturiana de la Energía, supporting Asturias's energy transition and the local hydrogen ecosystem.

THE CHALLENGE

Asturias is a coal-and-steel heartland that has to decarbonise without hollowing out the industry that built it. A standalone electrolyser risks producing hydrogen no one has committed to buy — and a coal plant like Aboño is the kind of asset a just transition usually retires rather than repurposes.

THE INNOVATION

EDP is building the Asturias H2 Valley: a 150 MW green-hydrogen production hub next to the Aboño power plant near Gijón, sized from the start around real industrial offtake rather than production alone — and sitting beside a converted power-plant boiler that can take hydrogen in its fuel mix.

THE OUTCOME

A full-stack production blueprint for coal regions in transition: an electrolyser, an anchor industrial consumer, and a feasibility path to scale from 150 MW toward 500 MW — with the permits already in hand and the build now going to tender.

Vanessa Hernández, EDP — on building the Asturias H2 Valley around the industry that will use its hydrogen.

The region

Asturias sits on Spain's northern coast — a compact, mountainous region that was for a century the country's coal-and-steel engine. Gijón and its surroundings still hold one of Spain's densest concentrations of heavy industry: steelmaking, refining, glass, zinc and chemicals, all clustered within a few kilometres of the same port and grid. That industry never left; what changed is that its fuel has to.

The Aboño thermal power plant, on the coast just outside Gijón, is emblematic of that shift. Built to burn coal, it is exactly the kind of asset a just transition has to reckon with — and exactly the kind of site EDP chose to build its hydrogen future on, rather than around. In July 2025 its Unit 2 came back online on natural gas, after all 30 coal burners were replaced with burners designed for natural gas and hydrogen. The region's advantage is that the customers, the infrastructure and the institutional will are already in the same place.

Asturias — region map

The opportunity

Asturias's advantage is that it is building production and demand as a matched pair — not standing up an electrolyser and hoping offtakers appear.

EDP sized the hub around industry that is already on the doorstep and already needs to decarbonise. As project director Rafael Cabañeros puts it, the region offered three things at once: a strong industry with real needs, mature energy infrastructure and security of supply, and a regional ecosystem — social, administrative and institutional — willing to support the project. Few places in Europe combine all three around a single site.

STARTING POSITION
~130 kt/yr
CO₂ the region's hydrogen hub is designed to avoid
Coal → gas + H₂
Aboño Unit 2 converted in 2025 with hydrogen-capable burners — repurposed, not retired

The solutions

Three moving parts make the hub work as one system. Open each to see the detail.

How it works as one system

From renewable power to industry and a retrofitted boiler. Hover any node to highlight it, click to open the detail.

BRANCHES TO
Renewable electricity
EDP Renewables
Renewable generation from EDP Renewables feeds the electrolyser, making the hydrogen genuinely green.
150 MW electrolyser
Asturias H2 Valley · Aboño
The first-phase 150 MW green-hydrogen plant beside the Aboño site, part-funded by the EU Innovation Fund, designed to produce ~20,000 t/yr and cut emissions by 99.98% versus displaced fossil fuels.
Green hydrogen
~20,000 t/yr
Roughly 20,000 tonnes of renewable hydrogen per year — the hub's output, sized around real industrial demand rather than production alone.
Industrial offtake
Cluster + Aboño boiler
Hydrogen goes to nearby industrial companies — used directly or converted into methanol and ammonia — and to the Aboño Unit 2 boiler as a first on-site consumer.
Aboño Unit 2 boiler
~10% H₂ planned in fuel mix
Aboño's Unit 2 was converted from coal in 2025, with burners designed to run on natural gas and hydrogen. The plan is to replace around 10% of the natural gas in the boiler with hydrogen from the hub — a coal-transition asset becoming a hydrogen consumer.
Methanol & ammonia
Industrial carriers
Industrial offtakers can convert the hydrogen into carriers such as methanol and ammonia — higher-value, easier-to-move forms for the cluster.
Co-transport
H₂ · O₂ · NH₃ · heat
EDP is exploring co-transport of hydrogen, oxygen, ammonia and heat to customers — treating the whole industrial cluster, not a single plant, as the offtaker.
Scale-up toward 500 MW
Feasibility study
A feasibility study is already looking past the first 150 MW toward 500 MW, if market conditions allow.
Knowledge exchange
With Upper Austria
Asturias is paired with Upper Austria — the other end of the Hy2Market production axis — sharing offtake-integration and retrofit know-how and drawing on electrolyser-deployment experience in return.

The process

Lessons learned

The central lesson from Asturias is about anchoring production in demand.

A hydrogen hub is only as bankable as the customers standing next to it — so EDP sized the Asturias H2 Valley around an existing industrial cluster and lined up a first on-site consumer in the converted Aboño boiler, rather than building capacity and waiting for a market to arrive. The second lesson is that the fossil past can be an asset, not just a liability: the permits, the grid connection, the skilled workforce and the political mandate for a just transition were already concentrated at Aboño. Reusing that foundation — converting a boiler instead of only decommissioning it — is what let a 150 MW project move from idea to tender with its consents already in hand.

The outcomes

150 MW
planned first-phase electrolyser capacity
~130 kt/yr
CO₂ / GHG the hub is designed to avoid
99.98%
design GHG reduction vs. displaced fossil fuels
500 MW
scale-up under feasibility study

Asturias offers the consortium a full-stack production answer — electrolyser, industrial offtake and a retrofitted power plant, permitted and heading to construction on the site of a former coal asset. With the environmental, access and urban permits granted and the EPC contract now at tender, the question shifts from "will it be allowed?" to "how fast can it scale?" — and a feasibility study is already looking past the first 150 MW toward 500.

Knowledge exchange

As a full-stack production region — electrolyser plus industrial offtaker — Asturias is paired with Upper Austria, the other end of the Hy2Market production axis. Knowledge flows in both directions across the network.

→
SHARING TO
Upper Austria · Austria

Industrial-offtake integration and power-plant retrofit know-how — how to size a hub around an existing industrial cluster and turn a coal-era boiler into a hydrogen consumer.

←
LEARNING FROM
Upper Austria · Austria

Electrolyser deployment and renewable-production experience, in exchange for Asturias's offtake and retrofit expertise.

IN THEIR WORDS

EDP is building a hydrogen hub called the Asturias Hydrogen Valley, of about 150 megawatts. Two years ago we were granted the main permits — the environmental permit, the access permit and the urban permit — and now we are discussing the EPC contract, the tendering.
Vanessa Hernández
EDP